|
File photo/Ian Gleadle
The suspected area was trenched to expose vertical
walls which could be studied.
Brightwater
Appeals: In January, three cities and two other
entities filed statements of appeal challenging
the adequacy of the Brightwater sewage treatment
plant Final Environmental Impact Statement (FEIS).
The appellants were the cities of Woodinville,
Bothell and Shoreline; StockPot Inc. along with
its parent company Campbell Soup Company of
New Jersey; and Sno-King Environmental Alliance
(SKEA), a local watchdog group opposed to the
State-Route-9 siting of the plant.
Snohomish County filed a notice of appeal in
early December, but on Jan. 20, the Snohomish
County Council voted 3 to 1 to drop its appeal.
And, over the course of several months, the
remaining appellants dropped their litigation
against King County, all except one: SKEA.
Those who dropped appeals worked with the county
to resolve issues of concern.
Woodinville agreement: Since the King-County
proposed sewage is to be located on 114 acres
about a half mile from Woodinville city limits
and about two miles from the city’s central
business district, Woodinville officials wanted
to be certain city residents and city resources
were protected from potential adverse impacts
of the plant, impacts not spelled out in the
project’s FEIS. Concerns prompted the
city to initiate the appeal process.
In April, however, the Woodinville City Council
voted unanimously to drop its appeal.
The city, instead, struck an agreement with
King County that addressed its concerns.
Particularly troublesome for city officials
was the fact that the City of Woodinville was
not a permit-issuing agency for the project.
From the very beginning, the city sought that
proverbial “seat at the table” that
would afford them, at the very least, the chance
to review and comment on Brightwater permits
and design.
Though the city has not been granted permitting-agency
status with approval authority at the site,
King County will allow the city an opportunity
to review and comment on all preliminary design
drawings for the Conditional Use Permit application
to Snohomish County. Woodinville’s input
is advisory, not binding. King County also commits
to involving Woodinville in mitigation discussions
related to the plant site. King County will
reimburse the city for staff time required to
review the design and permit submittals and
for staff involvement required for public meetings.
In the agreement, King County also reaffirmed
its commitment to no detectable odors at the
property line of the plant 365 days a year,
24 hours a day.
They also agreed to establish an Odor Reserve
Fund to be used to upgrade the odor system should
it not meet the standard of “no detectable
odors at the property line.” King County
will establish a peer review panel to determine
the dollar amount of the fund and a reasonable
period of time for holding the amount in reserve.
The agreement allows the city to be involved
in planning the construction traffic routes
as well as how routes are handled during an
emergency situation.
It also addresses truck routes once the plant
is operational.
SKEA appeal: SKEA hired world-renowned expert
known for earthquake hazard evaluation Robert
S. Yeats, Ph.D., to help review the seismic
studies presented in the project FEIS. The group
contended Yeats’ findings, in conjunction
with recent USGS (United States Geological Survey)
findings and LIDAR imagery, “produce substantial
evidence which has not been fully investigated
that the Route 9 treatment plant site lies within
the projection of the South Whidbey Island Fault.”
The group called for extensive geotechnical
and geological investigations to locate every
strand of the fault system within the project
area, determine the degree of activity of each
fault strand, and propose adequate mitigation
measures to prevent rupture of the pipeline
and destruction of the plant facilities.
Second addendum: According to the April 2 addendum,
a new temporary construction access road would
be built at the southern end of the plant site,
at the State Route-9 / State Route-522 westbound
ramp intersection. It would be located opposite
the existing westbound SR-522 interchange ramp
and would be restricted to Brightwater construction
traffic and possibly SR-9 construction traffic.
The addendum also identified the five portal
locations needed for tunnel construction for
the conveyance system or pipeline: near Point
Wells Road and 205th Street Northwest west of
Woodway; Ballinger Way Northeast and 19th Avenue
Northeast in Shoreline; Northeast Bothell Way
and Juanita Drive Northeast in Kenmore; Northeast
195th Street and 80th Avenue Northeast in Kenmore;
and North Creek Parkway and Northeast 195th
Street in Bothell.
Mitigation: Brightwater officials have said
for years that the proposed Brightwater wastewater
treatment system would be a good neighbor.
The Upper Bear Creek Community Council (UBCCC)
wanted a say in where the promised 80-plus million
mitigation dollars would be spent to compensate
for the adverse impacts caused by construction
and operation of the sewage plant. After all,
this industrial complex is going to be imbedded
in the Northshore community, a high resource
area worthy of protection, restoration and preservation,
said UBCCC President Geoff Clayton.
The group invited Michael Popiwny, architectural
design and mitigation manager for King County’s
Wastewater Treatment Division, to an April meeting
to discuss proposed mitigation projects. Popiwny
could commit to nothing, saying Brightwater
officials have heard mitigation requests for
the last several years.
According to Popiwny, the permitting agencies
and jurisdictions are the ones that have traction.
They issue permits with mitigation requirements
attached. Organizations and jurisdictions such
as the U.S. Army Corps of Engineers, the U.S.
Coast Guard, the National Oceanographic and
Atmospheric Administration Fisheries, the U.S.
Fish and Wildlife Service, the Washington State
Department of Ecology, the Washington State
Department of Fish and Wildlife, the Washington
State Department of Natural Resources, Puget
Sound Clean Air Agency, Snohomish County, Bothell,
Kenmore, Shoreline, Lake Forest Park, Woodway,
Woodinville (street-use permits), and the Burlington
Northern & Santa Fe Railroad et al. will
have their mitigation requests met for the exact
impacts to their area.
Another addendum: Addendum 3 contained new
seismic and geological information pertaining
to the siting, construction and operation of
the Brightwater facilities. County officials
said the findings did not substantially change
the analysis done in the original November 2003
final EIS.
Analysis indicated the Route 9 treatment plant
site met the recommended 0.5-kilometer separation
from a documented fault, since the South Whidbey
Island Fault (SWIF) probably runs from between
5 and 8 kilometers from the site.
Land formations in the plant-site area point
to something called the “Cottage Lake
lineament,” which does fall between 1
and 2 kilometers of the site, actually crossing
the northeast corner of the plant site footprint.
The addendum stated that USGS data suggests
the lineament has not been confirmed as a fault
or as an active fault.
Brightwater officials said, based on USGS findings,
should it be found to be an active fault, it
does not extend beneath any planned new buildings
or structures of the treatment plant, though
it may be located near the northeast corner
of the existing StockPot building.
By adhering to the requirements of the International
Building Code, the county said the plant site
would be designed for ground motions that are
consistent with the SWIF near the plant site.
Appeal hearing: On July 14, James O’Connor,
King County Hearing Examiner pro tem, listened
to testimony in the SKEA appeal of the King
County-produced Final Environmental Impact Statement
for the Brightwater sewage plant project.
Lawyer Jennifer Dold for SKEA said the county’s
FEIS was based on inadequate information. Seismic
information was missing, she said. There was
no information about the location of strands
of the SWIF that run near and through the proposed
plant site. There was no analysis of whether
the fault strands were active and no analysis
of surface rupture on the Route 9 site.
The county tried to “paper-over”
the inadequacy of the FEIS by releasing new
information in the form of addenda, she said.
The problem with the addenda, Dold maintained,
is there were no draft documents provided to
the public and other agencies for review. There
were no public-comment periods. There was no
requirement of the county to respond to comments,
nor need for the County Executive to consider
the information. The parade of new information
generated by King County after the FEIS was
released proves the FEIS was inadequate, she
said.
Patrick Mullaney, attorney for King County,
said King County witnesses would support the
adequacy of the FEIS. He said environmental-impact
statements require “a reasonably thorough
discussion of probable significant adverse impacts.”
They do not require an exhaustive level of detail.
They do not need to be a compendium of probabilities,
he said.
“SKEA information must be kept in perspective,”
said Mullaney. “It is only relevant if
it extends to a probable significant adverse
impact.”
The county believes there is an extremely remote
likelihood of the Brightwater plant or its conveyance
being impacted by seismic rupture. He said the
only earthquake related to the SWIF occurred
3,000 years ago. Even if it did occur, the nature
and effects of its impacts are not known, he
said.
To address the “ongoing parade of new
information” comment made by SKEA’s
lawyer, Mullaney said, “The project will
go through many levels of study. Testing and
analysis are ongoing.”
SKEA’s witness Dr. Yeats has been a practicing
earthquake geologist for over 30 years and author
of more than 135 papers in the field of geology,
including the standard textbook in earthquake
geology used worldwide. He said that faults
could be tens of meters wide. They are not necessarily
laser-thin lines. Faults can have strands that
shoot off in other directions. The way to determine
if a geological feature is a fault, whether
or not it is active or whether or not it has
faults that branch out from it is to trench
the suspected area with a backhoe or bulldozer
to expose vertical walls, which could then be
studied.
Yeats said, “Trenching is not an academic
exercise but part of what we do to insure the
safety of a large project.”
King County, on the other hand, told the hearing
examiner that the FEIS adequately explained
the seismic risks to the Brightwater plant site
and pipeline. The county maintained there is
a low probability of seismic risk. They have
over 320 miles of underground pipes and tunnels,
none of which has been seriously damaged in
the past 50 years, despite several large earthquakes.
They said risks can be avoided or the facilities
can be designed to accommodate them.
The county said it responsibly published new
seismic information when it was brought to their
attention. Based on the new information, they
have upgraded the seismic design of the plant.
They ask that the adequacy of the FEIS be upheld.
Appeal decision: On Aug. 3, Hearing Examiner
O’Connor ruled that the Final Environmental
Impact Statement for the Brightwater sewage
system was adequate as published on Nov. 19,
2003.
The examiner stated in his decision synopsis,
“In March 2004, King County received additional
information from the United States Geologic
Survey concerning the possible location of a
strand of a major earthquake fault on the Route
9 site.
“The availability of that new information
requires additional environmental investigation
and analysis prior to the use of the FEIS for
future governmental actions concerning permitting
and construction of the proposed wastewater
treatment plant on the Route 9 site.
“The additional information should be
provided to government agencies with jurisdiction
and to the public as either an addendum or as
a supplement to the FEIS, based on what the
new information shows.”
The county was required to trench the potential
fault.
Reactions to appeal decision: King County Executive
Ron Sims called the appeal decision “a
tremendous milestone in the long planning process
to build the needed sewage treatment capacity
for south Snohomish County and north King County.”
SKEA considered the decision “good news
and not-so-good news,” according to SKEA
member Glen Jones. The not-so-good news was
that the group’s appeal regarding the
adequacy of the project’s Final Environmental
Impact Statement (FEIS) was denied. The good
news was that the decision was subject to conditions;
namely, King County must trench the site to
investigate a suspected fault and must publish
its findings, Jones said.
Despite what may have appeared to be an acceptance
of the hearing examiner’s decision on
the part of King County and SKEA, both parties
appealed the Aug. 3 decision. The appeal hearing
is set for March 28, 2005.
Trenching: “The folding is consistent
with an active fault that runs through this
part of the world from Whidbey Island to the
Snoqualmie Valley,” said Craig Weaver,
Pacific Northwest coordinator for the USGS national
earthquake program.
Weaver’s statement was a preliminary
appraisal based on visual examination of a newly
dug trench meant to enable geologists and seismologists
to gather field evidence to better assess seismic
risk to the area in general, to the proposed
Brightwater sewage treatment plant in particular.
The excavation ran along the middle of a geological
feature known as Lineament 4, which is located
off State Route 9 just northeast of the former
Opus building, now part of the sewage plant’s
114-acre campus, in south Snohomish County.
The lineament extends through the northeast
corner of the StockPot soup building, also on
the plant site.
Though the fault line cuts through the northern
part of the proposed plant site, county officials
do not believe it will jeopardize the overall
Brightwater project. They will, said Christie
True, a Brightwater project manager, use the
latest and best information attained from this
study to enhance the plant’s structural
design. Contractors have already designed the
plant as if a fault existed, setting back plant
facilities 620 feet from the fault zone, she
said.
The county’s original siting criteria,
however, called for a 1,640-foot (.5 km) separation
of a plant site from a documented fault.
SKEA questioned whether an essential public
facility such as a sewage treatment plant should
be built near an earthquake fault. Other potential
treatment plant sites were eliminated from consideration
because of proximity to a fault. They believe
this site should be eliminated too.
Costs: With only about 30 percent of overall
design of the Brightwater sewage treatment system
complete, Brightwater officials released new
cost estimates. According to their report, the
planning-level cost estimate, prepared in 2001
and presented in the Final Environmental Impact
Statement of November 2003, was $1.35 billion.
The revised cost estimate is $1.48 billion.
County to issue a Supplemental EIS: On Dec.
21, Brightwater officials announced they would
issue a Supplemental EIS in late February or
early March. It would focus on the fault on
the north end of the Route-9 plant site. This
document, said Christie True, would be in answer
to the hearing examiner’s August appeal
decision.
There will be a public comment period once
the draft document is published. The county
will respond to public comments and then issue
a final Supplemental EIS, probably in May, True
said.
True acknowledged there is yet another lineament
on the south end of the Route 9 site. It may
run parallel to the fault line discovered in
fall. She said this lineament is a weaker feature
than Lineament 4. She said it was difficult
to detect because junk cars in the area interfered
with the LIDAR imaging.
“We probably will not study it,”
said True. “We will assume it is active
and act accordingly.”
SKEA believes the new lineament should be trenched.
They feel it could impact where facilities can
be sited or whether the Route-9 site is appropriate
at all.
SKEA member Linda Gray said, “Assuming
it is active isn’t enough. The only way
they can truly identify where it goes and where
the branching is, is by trenching.”
Dr. Yeats, retained by SKEA, said upon hearing
about the Supplemental EIS, “I wish we
could get them to take seriously the problems
of lineaments along the conveyance route. There
are at least two, and I feel that these both
have the potential to be active faults. I wonder
what this means for King County getting catastrophe
insurance for this project.”
True said conveyance tunnels generally hold
up very well during earthquakes. They are so
deep they tend to move when the earth moves.
Should a pipe be damaged by a quake, she said,
the system would kick into its emergency protocols,
which would shut down the flows. She also said
there is no way to avoid the pipeline crossing
lineaments in the Pacific Northwest. The USGS
Open File Report 2004 mentioned a lineament
along Ballinger Way. True said she did not know
whether the Supplemental EIS would deal with
that particular lineament.
|