|
Staff
photo/Ian Gleadle
Road improvements along the north leg of SR-202
are set to begin. The project will add a new
northbound lane from Little Bear Creek Parkway
to the south end of the SR-522 overpass. It will
also add another southbound left turn lane toward
Little Bear Creek Parkway.
Photo by Scott Knutson
Road improvements on SR-202 between Little Bear
Creek Parkway and the SR-522 westbound off ramp
will begin this month, as the sign above proclaims.
The city awarded a construction contract
to West Coast Construction Company to complete
road improvements on State Route 202 (SR-202)
between Little Bear Creek Parkway and the
SR-522 westbound off ramp. The improvements
are part of the city’s Bottle Neck
Relief Project and should begin within
the next six weeks. Though the contract
stipulates a fall completion, the majority
of the road construction should be done
within a couple months.
The project will add a new northbound
lane from Little Bear Creek Parkway to
the south end of the SR-522 overpass. The
lane will provide extra capacity for vehicles
lining up at the SR-522 southern ramp’s
traffic signal.
The project will also add another southbound
left turn lane toward Little Bear Creek
Parkway. The extra turn lane is expected
to reduce the congestion that occurs when
the line of vehicles turning left onto
the Parkway block the through southbound
lanes. The city hopes that additional left
turn capacity will encourage more drivers
to use Little Bear Creek Parkway for access
into the Central Business District.
In addition to road widening, improvements
include curb, gutter, sidewalks, landscaping,
irrigation, and other associated work.
City Manager Pete Rose told the City Council
on April 10 that construction would bring
a “somewhat limited interruption
to traffic.”
The city’s Public Works Director
Mick Monken said drivers would experience
some disruption but that the scope of a
project done last year to construct a wall
along a portion of the northbound SR-202
lanes included widening the shoulder.
“Now the contractor has a place
to work, off the main travel area,” said
Monken.
Two-thirds of the project funding will
come from a grant from the Washington State
Transportation Improvement Board (TIB).
“It was approved last November,” said
Monken. “The City of Woodinville
competed against hundreds of projects for
the grant.”
The TIB will provide $498,825. The city
is responsible for the remaining balance
of $249,413.
The city received four bids for the project
ranging from $680,216.60 to $724,139.43.
The engineer’s estimated project
cost was $687,240. West Coast’s low
bid of $680,216 came in $7,023 under the
engineer’s estimate.
The contractor has performed other construction
projects for the city: the Bottle Neck
Relief Project Sound Transit Flyer stop
(this year), the SR-202 / Little Bear Creek
Parkway intersection improvement (2003)
and the NE 175th Street westbound right
turn pocket extension (2003).
“Woodinville has a very good working
relationship with West Coast Construction,” said
Monken. “Their field and management
teams worked very closely with the city.
When you work on any project, there are
always a few unexpected situations. West
Coast has a lot of experience that enables
them to come up with quick, economical
solutions.”
Questions about the project can be directed
to Bill Henry, project manager, at (425)
489-2700 ext. 2296.
This project will complete SR-202 road
improvements north of the railroad trestle.
Upon completion, the city expects to see
immediate traffic improvements.
|