| Preliminary
clearing and grading began last week on King
County’s biggest road project of the
year – the construction of a new Tolt
Bridge. Actual construction activities will
start after the Fourth of July holiday.
The new $27.5 million bridge will span the
Snoqualmie River just west of Carnation
and approximately 165 feet upstream from
the current historic bridge on Northeast
Tolt Hill Road. The new bridge will be
wider and safer for motorists and pedestrians,
plus is designed to reduce river flooding
in that location.
This is the largest construction project
for the King County Road Services since the
completion of the new Elliott Bridge in 2005.
Construction of the new Tolt Bridge is expected
to last for up to two years. The Roads Division
is staging the construction to avoid fish-spawning
seasons and to minimize traffic disruptions
for local residents.
One of the goals is to keep Northeast Tolt
Hill Road open to traffic as much as possible
throughout construction. Motorists can expect
one 2-3 week closure this summer, and then
another in the spring of 2008. There could
also be occasional short closures for maintenance
work on the old bridge, but otherwise the
road should remain open throughout the majority
of the construction period.
The first activity at the project site will
be removal of brush and some trees on the
west side of the bridge near the intersection
of Northeast Tolt Hill Road and West Snoqualmie
River Road Northeast.
Early next month, the contractor will be
placing a huge order for the steel that will
go into the new bridge. The order is so large
that project managers estimate it will take
nine months to fabricate and then deliver
to the site.
The county has been working to replace the
Tolt Bridge for many years. Extra time was
needed to gather funding for the costly project,
negotiate agreements with numerous agencies
on environmental issues, and to address residents’ concerns
about the design of a bridge that would replace
a community landmark.
The existing bridge is more than 80 years
old and needs frequent maintenance, often
requiring traffic closures. It has limited
sight distance, a narrow roadway and restricted
weight limits. It also does not meet current
seismic, safety, or roadway design standards.
In addition to constructing a modern bridge,
this project will widen and realign Northeast
Tolt Hill Road both east and west of the
new bridge to increase sight distance and
safety.
The plans call for a 970-foot-long bridge
made up of two 300-foot-long trusses over
the west side of the river and the river
itself, and a concrete girder section on
the east side.
The twin trusses will echo the historic
look of the existing bridge. The new bridge
will have a cast-in-place, 40-foot-wide concrete
deck supported by six double-column concrete
piers.
An eight-foot-wide shoulder for pedestrians
and bicyclists will be added on both sides
of Northeast Tolt Hill Road and the bridge.
An open-rail type barrier will be built on
both sides of the new bridge for safety.
For more information: http://www.metrokc.gov/kcdot/roads/cip/projectdetail.aspx?cipid=200394
|